WORKING WEEK - May / June 2000
Water Tanks
Married quarters upgrade Mens'
changing rooms and showers redecoration
 |
|
An early start ..... Although
the Monday was a public holiday, the weather forecast suggested that
we should make an early start to the working week early and so a large
number of club members were press ganged into going up to the water
tanks to carry out a day's maintenance work.
The Penwyllt
water supply is dependent upon flow from the river into some settling
tanks and over a period of several years the dam which diverts the
water had reached a state of imminent collapse. The aim of the
exercise was to install some gabions and fill them with rocks to
stabilise the dam.
Levelling
the river floor at the dam base before installation of the new gabions
|
|
A team effort ..... With
each gabion sized at 2m3, we needed rocks to the volume of
about 9m3 to complete the job. Thanks to a team effort
from about fifteen people and under the guidance of John Lister, four
of the units were installed just in front of the existing, dam which
has gradually been collapsing and preventing water from flowing into
the collection tanks.
An estimated 16 tonnes of rocks were
shifted from upstream into the gabions. Allan Richardson and Andy
Amatt had a competition to see who could shift the largest rock,
whilst others contented themselves with smaller items. Lastly, several
barrow loads of pebbles were poured into each gabion to fill up the
gaps.
Filling the gabions with rocks to stabilise the
dam wall  |
|
 |
 |
|
Digging out the water tank
..... We also had to set about digging out the top
water tank. During floods, this tank fills with rocks and sediment,
making it ineffective as the first stage of settlement. Dave Edwards,
and Simon Amatt abetted by the dog, cleared the tank, Keith Goodhead
cleared upstream blockages whilst Graham Christian and others worked
downstream.
By the end of play, we had successfully restored
the flow through the tank and reconnected the supply. Since we also
had a vehicle up there, the opportunity was taken to tidy up the area
and in particular to remove all the unsightly lengths of pipe which
had been lying around the tanks for some years.
Milo
(the one with the biggest ears) supervises the clearing out of the top
water tank
|
|
Improved protection ..... The
water supply to the club is carried from the tanks by a 2"
alkathene pipe which is for the most part buried underground for
protection against mechanical damage and freezing in cold weather. In
one or two places however, it has become exposed, one of these places
being where the pipe crosses the river just downstream from the third
settling tank.
Improved protection was achieved by placing a
half-sized unit just in front of the exposed section of pipework so
that it will then cover in with natural deposition of silt and rocks.
Clark Friend tries to collapse the downstream
gabion  |
|
 |
|